1. MRP stands for
A. Master Resources Production
B.
Management Reaction Planning
C.
Materials Requirements
Planning
D.
Manufacturing Resource
Planning
2. What does ERP stand for?
A.
Expanse Research Project
B.
Enterprise Research Planning
C.
Enterprise Resource Planning
D.
Expanse Resource Project
3. The objectives in developing an MRP include:
A. To
maintain the desired level of customer service by maintaining finished goods
inventory levels or by scheduling to meet customer delivery requirements
B. To
make the best use of material, labor , and equipment
C. To
maintain inventory investment at the required levels
D. All of
the above
4. Which of the following has the least integration of
information systems?
A.
Enterprise Resource Planning
B.
Web-Integrated Enterprise
Resource Planning
C.
Materials Requirements
Planning
D.
Manufacturing Resource
Planning
5. Which of the following is
an output of materials requirements planning?
A.
Work Orders
B.
Master Production Schedule
C.
Bills Of Materials
D.
All of the above
6. MRP – II is accurately
described by
A. MRP software designed for services
B. MRP with a new set of computer
programs that execute on micro-computers
C.
MRP augmented by other
resources variable
D. Usually employed to isolate
manufacturing operations from other aspects of an organization.
7. The information needed to develop an MPR
includes
A.
The production plan
B.
Forecasts for individual end items
C.
Actual orders received from
customers and for stock replenishments
D.
All of the above
8. The list of quantities of components,
ingredients, and materials required to produce a product is the
A.
Master Schedule.
B.
Engineering Change Notice.
C.
Bill-Of-Materials.
D.
Purchase order.
9. Which of the
following is an advantage of ERP (enterprise resource planning) systems?
A. Need to change existing business practices
B. Lengthy implementation processes
C. Complex operating processes
D. Organizational
flexibility and agility
10. The first step in preparing an MPS is:
A.
Develop a preliminary MRP
B.
Check the preliminary MRP
against available capacity
C.
Resolve differences
between the preliminary MPS and the capacity available
D.
Develop a rough-cut capacity
plan
11. Which is not the
objectives of MRP -I ?
A.
Decrease efficiency
B.
Inventory reduction
C.
Realistic commitments
D.
Reduction in production and
delivery lead times
12. Identify terminology of MRP – I
A.
MRP logic
B.
Time bucket
C.
BOM
D. Product
13.
The MRP
forms a vital link between sales and production as follows:
A.
The MRP makes possible valid order
promises
B.
The MRP is a plan of what is to be
produced and when
C.
The MRP is a contract between
marketing and manufacturing.
D.
All of the above
14.
In the
_________ environment, many different end items are made from a small number of
components.
A.
Make-to-Stock
B.
Make-to-Order
C.
Assembly-to-Order
D.
Engineer-to-Order
Answers-
1-C,2-C,3-D,4-C,5-A,6-C,7-D,8-C,9-D,10-A,11-A,12-B,13-D,14-B.